Apache Point Observatory 3.5m User's Committee Meeting May 8, 2000 Attending: Jeff Brown, Lew Hobbs, Ed Turner, Michael Strauss, Chris Stubbs, Bruce Gillespie, Rene Walterbos Not attending: Alan Uomoto Accomplishments of the April shutdown: Worked on mounting of new secondary. Various parts were replaced and tests carried out. A few engineers who are working on the new topend came to the site, and were able to see the details of the current system. Things appear to be better, but there are problems with image motion that started appearing over the weekend. Problems Might these be due to water in the PMSS hydraulic lines? May shutdown plans (May 15-18) are described in the appendix below (from Mark Klaene). There may be work both on baffling and on the DIMM, by Chris Stubbs and his team. They will be using an instrument that measures rapid image motion, to determine what is causing some of the problems we've been seeing recently. July shutdown (July 10-28) will focus on work on the astigmatism on the primary mirror, as well as service work on the bearings of the telescope. See the appendix for the list of topics to be addressed at this time. The status of the new topend: There are a lot of resources in place at the site, UW, and UC, but there needs to be some coordination of the various people. There is a plan to go ahead and order the square truss for the end of the telescope, to get things rolling. Right now, the secondary is held up with steel rod tubes under tension, as opposed to the traditional metal vanes. It is not clear which should be used for the new top end. There is a phone con tomorrow to make decisions of which ports each of the new instruments planned (in particular, Chris Stubbs' wide-format camera, and the laser for Chaos) will go. There is a fair amount of engineering details to go through to get this straight. To permanently mount an instrument at a non-Nasmyth port gives very good efficiency, but then you needed a dedicated rotator and guider, an additional $50 to $100K expense. If we hang too many instruments on, it is possible it will cause troubles with the telescope drives. Stubbs: this ties directly into questions of the long-range plan for the telescope. Therefore, it would be very good for the user's committee to put together a straw-man five-year plan for instrumentation. Gillespie: If we could get a rotator in place, we could put GRIM onto a non-Nasmyth port right now. Stubbs is thinking about switching rotators between what he's building for his large camera, and the current one at the Nasmyth port. Gillespie will get center of mass and inertial parameters for the existing instruments, information necessary to understand the specifications of the rotators we would need to get. Observing efficiency enhancement effort: We are thinking about using a tool from the SDSS folks whereby you can clock how much time you spend doing different activities, to see where overheads are going. This would be very useful to figure out which items can be tackled to try to improve efficiency. Director's Discretionary time for SDSS and other follow-up is getting used; 5 or 6 proposals were received, and four half-nights were assigned this quarter. Strategic plan for the 3.5m once the SDSS finishes (roughly 5 years from now) is something that we should start thinking about now. The issue is that there are a lot of people on the SDSS payroll who are taking part in 3.5m activities (some of whom are split 50-50 between the two projects). Moreover, there are a lot of fixed operating costs on the mountain (plowing the road to the observatory, the phone system, etc), which the 3.5m would have to take on by itself. We need to maintain a critical mass of people and expertise on the mountain; without the SDSS, this will all become more expensive. Should we go to much more austere operations? Should we make this a more specialized (as opposed to general-purpose) telescope? This is an issue for all the participating institutions to start thinking about. Stubbs: DIS upgrade: we're going to leave the existing optics, and replace detectors and electronics. We will not buy off-the-shelf electronics (which was the initial plan); rather, we'll borrow from electronics of the wide-field camera. We're talking to Alan Uomoto about a SITE detector on the blue side; the red side will use a chip available at UW. No corrections to last month's meeting minutes. The next User's Committee meeting will be held on June 19 at 11:30 AM East Coast Time. ***********************Appendix********************************* From Mark Klaene, May shutdown plans. 1. repair rotator runaways (R&R motor?) (daytime 1-2 days JD,MK,DW) 2. drop vent tubes 1/2" to see effect on astigmatism and high freq oscillations (1/2 night all) 3. S-H dat on full altitude sweep ( 1/2 night Jeff M) 4. further 2dry testing TBD (1/2 night JD and Jeff M) 5. Install datec monitor for PMSS (daytime peter D and Dave woods) 6. mirror cell warping test TBD (daytime JD and Tim Rennick) 7. fast guiding metrology testing (3/4 night) From Mark Klaene: Tasks for the July shutdown: pull M1 repair hardpoint dimples Wash M1 remove perimeter seal install encoders on M1 and perhaps M3. clean up PMSS wiring service main az bearing cont work on mirror cover automation APO APO APO APO APO Apache Point Observatory 3.5m APO APO APO APO APO This is message 434 in the apo35-general archive. You can find APO the archive on http://www.astro.princeton.edu/APO/apo35-general/INDEX.html APO To join/leave the list, send mail to apo35-request@astro.princeton.edu APO To post a message, mail it to apo35-general@astro.princeton.edu APO APO APO APO APO APO APO APO APO APO APO APO APO APO APO APO APO