Largely due to longer than anticipated delivery times for some
components of the modified (safety enhanced) mountings of the
secondary and tertiary, resumption of science operations will
be delayed significantly beyond the previously announced date of
November 25. The additional shutdown time may be about two weeks,
which would be until approximately December 8. A more definite
schedule will be announced when it is available.
Ed Turner
APO APO APO APO APO Apache Point Observatory 3.5m APO APO APO
APO
APO This is message 394 in the apo35-general archive. You can find
APO the archive on http://www.astro.princeton.edu/APO/apo35-general/INDEX.html
APO To join/leave the list, send mail to apo35-request@astro.princeton.edu
APO To post a message, mail it to apo35-general@astro.princeton.edu
APO
APO APO APO APO APO APO APO APO APO APO APO APO APO APO APO APO