Subject: New System for Scheduling EN00 Shutdowns
From: elt@astro.Princeton.EDU
Submitted: Wed, 2 Jul 1997 10:24:54 -0400 (EDT)
Message number: 151
(previous: 150,
next: 152
up: Index)
An extensive set of engineering projects intended to improve the performance
of the APO 3.5m and its instrumentation to levels which are generally
competitive with the best other 4m class telescopes and which are uniquely
powerful in some respects is now well underway. These include both those
upgrades described in the "Three Year Plan" and remediation of some problems
discovered since its adoption. A later message from Chris Stubbs will
summarize the results to date. Fast progress in this effort is being given
very high priority, and the necessary shutdowns of the telescope are being
accepted as an unavoidable cost. We are continuing to try to optimize the
procedures by which we simultaneously use the telescope for science while
this engineering campaign is in progress.
The difficulties with the schedule for the planned 3Q1997 engineering
shutdown of the 3.5m which were discussed in two preceding messages
are not unique. In fact, we have encountered quite similar problems with
the three previous major engineering shutdowns: namely, the June shutdown
for installation of the new guider, the April shutdown for installation
of a new support system for the primary, and the Dec-Jan shutdown for
replacement of the enclosure rotation wheels and re-aluminization of the
optics.
There are two basic problems:
1) Despite our best efforts, it has proven impossible to accurately predict,
months in advance, the date on which all necessary preparations for a
particular shutdown will be completed. These include receiving parts,
preliminary work not requiring telescope shutdown and scheduling of
critical personnel to work on the shutdown. Often the completion of
such preparations is affected by matters entirely beyond the control
of the Observatory and/or which are inherently unpredictable. In
practise, since things always take longer than one expects, we have
never been fully ready at the beginning of a major shutdown. This
results in less efficient use of the shutdown time and thus ultimately
reduces available science time.
2) Despite often heroic efforts by those working on a shutdown, it usually
has proven impossible to complete all planned engineering tasks
within the scheduled duration of the shutdown. This is partly due to
problem #1, not being fully ready to start. However, it is also due
to other factors such as absence of a detailed understanding of the tasks
involved months in advance, growth in the scope of planned work as time
passes, discovery of unanticipated problems in the course of the
shutdown work, need for clear skies for some tasks (typically as the
telescope is being returned to service) and so forth. This results in
both disappointment for users scheduled to use the telescope immediately
following the shutdown and in enormous stress on those working on the
engineering tasks as they strive to meet what may well be an unrealistic
goal.
Based on experience and such considerations, all those immediately
concerned have concluded that the present system of scheduling extended
shutdowns (EN00 time) is not working in an acceptable way. We will
therefore try one or more different systems in future quarters.
A specific proposal is described below. The Users Committee will discuss
it on July 14 and perhaps in subsequent meetings. Please give your
comments and suggestions to your institutional UC representative and/or
email them to me.
The proposed new system for dealing with EN00 time is as follows:
1) No EN00 time will be explicitly scheduled in each quarter; only EN01
time will be scheduled specifically (EN01 is typically a single night
set aside for routine engineering tasks on a regular basis, e.g.,
pointing models, and usually amounts to about 7% of all available
time).
2) When *all* preparations for a given major engineering task requiring
extended (more than one night) shutdown of the telescope are *complete*,
those planning to carry out the work will request a shutdown of some
specific duration, based on their best estimate of how long it will take.
3) The shutdown will then be scheduled and announced at least, but very
often no more than, two weeks in the future (2 weeks notice) and will
simply pre-empt whatever science programs are scheduled for that period.
4) From the Observatory point-of-view, time lost in this way will be like that
lost to bad weather or equipment problems in that there will be no attempt
to provide compensating time. (Of course, institutions may arrange such
compensation internally if they wish.) Of course, pre-empted time will be
accounted as engineering time and not charged to the affected institutions;
in this respect, it is not like time lost to weather or equipment problems.
5) In scheduling such pre-emptory engineering time, account may be taken of
programs that are of particularly high priority (as determined by
institutional TACs) or which would produce data not easily obtainable
at other times (e.g., occultations, observations coordinated with other
observatories or spacecraft). Programs which are believed to merit such
special protection should be explicitly identified in the proposals and
institutional scheduling requests. However, it should be understood that
no program can be certainly exempted (i.e., no promises) from cancellation
due to EN00 engineering shutdowns.
This system should solve the first problem described above and somewhat
alleviate the second (which probably cannot be entirely avoided). Although
it will doubtless produce inconvenience and disappointment for those whose
observing time is canceled with as little as two weeks notice, this should
be viewed in perspective with the fact that observing time is often lost with
much less (even zero) notice to weather and equipment problems. The overall
gain in total science time available (due to more effective use of shutdown
time) and in telescope/instrument performance (due to the engineering
improvements themselves) should also help to ease the blow.
Many other ways of dealing with this scheduling problem are certainly
possible, and several of them have been proposed and discussed. However,
the one described above seems to me to be the simplest and most effective.
I look forward to receiving your comments on it.
Ed Turner
APO APO APO APO APO Apache Point Observatory 3.5m APO APO APO
APO
APO This is message 151 in the apo35-general archive. You can find
APO the archive on http://www.astro.princeton.edu/APO/apo35-general/INDEX.html
APO To join/leave the list, send mail to apo35-request@astro.princeton.edu
APO To post a message, mail it to apo35-general@astro.princeton.edu
APO
APO APO APO APO APO APO APO APO APO APO APO APO APO APO APO APO